Construction of Slope Protection Structure24CC0290

Construction/Improvement of Slope Protection Structure and Waterways, Brgy. Pritil, Guiguinto, Bulacan

Construction/Improvement of Slope Protection Structure and Waterways, Brgy. Pritil, Guiguinto, Bulacan is a DPWH-tracked public work in GUIGUINTO (BULACAN), BULACAN, Region III. Reported contract value: ₱98,999,656.35. Status: Reported complete (DPWH). Contractor on record: TOPNOTCH CATALYST BUILDERS INC / ONE FRAME CONST INC. Figures trace to sumbong.

GUIGUINTO (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Waterways and Flood Control Structure along Guiguinto River, Brgy. Malis, Guiguinto, Bulacan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007285

₱1,480,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005755

₱1,178,933.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0017916

₱440,428.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007286

₱137,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0005756

₱95,671.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

NCA NCA-ROXII-24-0017122

₱99,000.00 · FY2024

Released to Banga National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

15 projects · ₱1.5B total · 17 flags

4. Implementation

Contract Amount

₱98,999,656.35

Progress

Reported complete (DPWH)

Start Date

April 25, 2024

Target End

January 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.