Roads21KB0134

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG MARAMAG-MARADUGAO ROAD, K1568+484-K1569+000 (R/S), K1568+484-K1568+1030 (L/S), K1569+029-K1569+400 (B/S0, K1569+423-K1569+582 (R/S), K1569+586-K1569+860 (R/S), 1569+870-K1569+950 (B/S), COLAMBUGON, M

CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG MARAMAG-MARADUGAO ROAD, K1568+484-K1569+000 (R/S), K1568+484-K1568+1030 (L/S), K1569+029-K1569+400 (B/S0, K1569+423-K1569+582 (R/S), K1569+586-K1569+860 (R/S), 1569+870-K1569+950 (B/S), COLAMBUGON, M is a DPWH-tracked public work in Bukidnon 2nd DEO, Region X. Reported contract value: ₱22,140,160.00. Status: Reported complete (DPWH). Contractor on record: KIOKONG CONST AND DEVELOPMENT CORP. Figures trace to dpwh.

Bukidnon 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System - Water Diversion Canal at Downstream Portion of Taganibong Creek, Maramag, Bukidnon
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱407,327,000.00 · FY2021

Released to Batangas 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱22,140,160.00

Progress

Reported complete (DPWH)

Start Date

September 24, 2021

Target End

May 30, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.