Buildings and Facilities24DQ0114

CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING, ZAPOTE 3 (FORMERLY ZAPOTE 5), BACOOR CITY, CAVITE

CONSTRUCTION(COMPLETION) OF MULTI-PURPOSE BUILDING, ZAPOTE 3 (FORMERLY ZAPOTE 5), BACOOR CITY, CAVITE is a DPWH-tracked public work in Cavite 3rd DEO, Region IV-A. Reported contract value: ₱14,204,105.47. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ALMAKAR BUILDERS. Figures trace to dpwh.

Cavite 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱8,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure and Other Improvements, Brgy. Molino 4, Zapote River, Bacoor, Cavite
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-24-0016076

₱310,523,000.00 · FY2024

Released to Regional Office - III (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

168 projects · ₱4.5B total · 0 flags

4. Implementation

Contract Amount

₱14,204,105.47

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

October 14, 2024

Target End

July 10, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.