Roads19L00083

CONSTRUCTION OF CONCRETE ROAD-MONKAYO-COMPOSTELA ROAD, PACKAGE C, COMPOSTELA VALLEY

CONSTRUCTION OF CONCRETE ROAD-MONKAYO-COMPOSTELA ROAD, PACKAGE C, COMPOSTELA VALLEY is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱59,466,309.80. Status: Reported complete (DPWH). Contractor on record: PREMIUM MEGASTRUCTURES INC. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱59,466,309.80

Progress

Reported complete (DPWH)

Start Date

July 17, 2019

Target End

June 20, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.