Flood Control and Drainage21LH0084

CONSTRUCTION OF CONCRETE REVETMENT ALONG TALOMO RIVER, RIVERSIDE SECTION, CALINAN DISTRICT, DAVAO CITY (STA. 0+000-STA. 0+500)

CONSTRUCTION OF CONCRETE REVETMENT ALONG TALOMO RIVER, RIVERSIDE SECTION, CALINAN DISTRICT, DAVAO CITY (STA. 0+000-STA. 0+500) is a DPWH-tracked public work in Davao City 2nd DEO, Region XI. Reported contract value: ₱92,653,424.13. Status: Reported complete (DPWH). Contractor on record: ABU CONST 22313. Figures trace to dpwh.

Davao City 2nd DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱23,100,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Bago River, Bago Aplaya Section, Both Bank, Davao City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱404,461,000.00 · FY2021

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱92,653,424.13

Progress

Reported complete (DPWH)

Start Date

April 28, 2021

Target End

January 26, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.