GAA 2024 SSP24M00159

1. CONSTRUCTION OF RIVER BANK SLOPE PROTECTION STRUCTURE ALONG MARBER RIVER (UPSTREAM) STA 0+000-STA 0+452.381, BRGY.STO. NIÑO, KORONADAL CITY, SOUTH COTABATO (PHASE 1);2. CONSTRUCTION OF RIVER BANK SLOPE PROTECTION STRUCTURE ALONG MARBER RIVER (UPSTREA

1. CONSTRUCTION OF RIVER BANK SLOPE PROTECTION STRUCTURE ALONG MARBER RIVER (UPSTREAM) STA 0+000-STA 0+452.381, BRGY.STO. NIÑO, KORONADAL CITY, SOUTH COTABATO (PHASE 1);2. CONSTRUCTION OF RIVER BANK SLOPE PROTECTION STRUCTURE ALONG MARBER RIVER (UPSTREA is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱277,068,415.40. Status: Past target date (DPWH On-Going). Contractor on record: ABU CONST. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱277,068,415.40

Progress

Past target date (DPWH On-Going)

Start Date

September 2, 2024

Target End

August 2, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.