Roads18M00059

PAVING OF UNPAVED ROADS SURALLAH LAKE SEBU MAITUM ROAD, CHAINAGE 3100 CHAINAGE 5340, LAKE SEBU, SOUTH COTABATO

PAVING OF UNPAVED ROADS SURALLAH LAKE SEBU MAITUM ROAD, CHAINAGE 3100 CHAINAGE 5340, LAKE SEBU, SOUTH COTABATO is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱193,000,000.00. Status: Reported complete (DPWH). Contractor on record: ABU CONST. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱193,000,000.00

Progress

Reported complete (DPWH)

Start Date

June 14, 2018

Target End

August 16, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.