Bridges17L00121

WIDENING (2 INTO 4 LANES) OF HIJO BRIDGE (B00209MN) INCL. APPROACHES & RROW ALONG SURIGAO-DAVAO COAS

WIDENING (2 INTO 4 LANES) OF HIJO BRIDGE (B00209MN) INCL. APPROACHES & RROW ALONG SURIGAO-DAVAO COAS is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱123,630,425.15. Status: Reported complete (DPWH). Contractor on record: ABU CONST 22313. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Money Trail

1. Appropriation

GAA FY2017 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱123,630,425.15

Progress

Reported complete (DPWH)

Start Date

May 2, 2017

Target End

January 18, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.