Roads22CJ0168

ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE ROMULO H-WAY - K0140 + 754 - K0141 + 024, K0141 + 172 - K0141 + 713

ASSET PRESERVATION PROGRAM PREVENTIVE MAINTENANCE ROMULO H-WAY - K0140 + 754 - K0141 + 024, K0141 + 172 - K0141 + 713 is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱28,704,391.66. Status: Reported complete (DPWH). Contractor on record: NORTHERN BUILDERS. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Along Camiling River Left Bank Phase II-2, Poblacion D to G Section, Poblacion D to G, Camiling, Tarlac
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-A-22-0002427

₱41,059,244.00 · FY2022

Released to Tarlac DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

431 projects · ₱38.3B total · 3 flags

4. Implementation

Contract Amount

₱28,704,391.66

Progress

Reported complete (DPWH)

Start Date

March 23, 2022

Target End

June 3, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.