Construction of Flood Mitigation Structure23EE0030

Construction of Buluang Bridge I Flood Control Structure, Sta. 0 + 044.64 - Sta. 0 + 095.00 (UPSTREAM - BK.I), Sta. 0 + 000 - Sta. 0 + 095.00 (UPSTREAM - BK. II), Sta. 0 + 000.00 - Sta. 0 + 026.00 (DOWNSTREASM - BK. II), Busuanga, Palawan

Construction of Buluang Bridge I Flood Control Structure, Sta. 0 + 044.64 - Sta. 0 + 095.00 (UPSTREAM - BK.I), Sta. 0 + 000 - Sta. 0 + 095.00 (UPSTREAM - BK. II), Sta. 0 + 000.00 - Sta. 0 + 026.00 (DOWNSTREASM - BK. II), Busuanga, Palawan is a DPWH-tracked public work in BUSUANGA (PALAWAN), PALAWAN, Region IV-B. Reported contract value: ₱8,884,656.00. Status: Reported complete (DPWH). Contractor on record: MAC BUILDERS CIVIL ENGINEERING CONST. Figures trace to sumbong.

BUSUANGA (PALAWAN), PALAWAN, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱9,250,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Buluang Bridge I Flood Control Structure, Sta. 0 + 000 - Sta. 0 + 225, Busuanga, Palawan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-23-0019306

₱15,036,914.00 · FY2023

Released to 0000000 Davao Oriental - State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

108 projects · ₱653.6M total · 0 flags

Other projects by this contractor

No sat.

CONCRETING OF SITIO CASTILLA, BRGY. STO. NINO FMR, BUSUANGA, PALAWAN

Palawan 1st DEO, Region IV-B

2024₱14.9M
Reported complete (DPWH)
No sat.

PACKAGE 3-CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDINGS IN:1. LAJALA ELEMENTARY SCHOOL, BARANGAY LAJALA, CORON2. BIONG ELEMENTARY SCHOOL, BARANGAY OSMENA, CULION3. BALDAT ELEMENTARY SCHOOL, BARANGAY BALDAT, CULION

Palawan 1st DEO, Region IV-B

2024₱14.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BANAYBANAY I AND BANAYBANAY II, SAN JOSE, BAT

Batangas 4th DEO, Region IV-A

2024₱14.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF ROAD, BARANGAY CATANDALA, IBAAN, BATANGAS

Batangas 4th DEO, Region IV-A

2025₱14.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF CONCRETE ROAD, BARANGAY DAYAPAN, IBAAN, BATANGAS

Batangas 4th DEO, Region IV-A

2025₱14.4M
Past target date (DPWH On-Going)
No sat.

PACKAGE 1-CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDINGS IN:1. BALOGO ELEMENTARY SCHOOL, BARANGAY BALOGO2. ARACELI NORTH CENTRAL SCHOOL, BARANGAY POBLACION, ARACELI, PALAWAN

Palawan 1st DEO, Region IV-B

2024₱9.9M
Past target date (DPWH On-Going)
View all 108 projects →

4. Implementation

Contract Amount

₱8,884,656.00

Progress

Reported complete (DPWH)

Start Date

April 18, 2023

Target End

July 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.