Construction of Flood Mitigation Structure22FG0046

Construction/Improvement of Flood Control Structure along Sagpon River, Sta. 0+480 - Sta. 0+784.50 bothside (Upstream), Sta. 0+525 - Sta. 0+707 (L/S), Sta.0+743 - Sta. 0+799 (LS), Sta. 0+555 - Sta. 0+643 (R/S), Sta. 0+682.50 - Sta. 0+799 (R/S), Sta. 2+055 - Sta. 2+617 both side (Downstream), Tigaon, Camarines Sur

Construction/Improvement of Flood Control Structure along Sagpon River, Sta. 0+480 - Sta. 0+784.50 bothside (Upstream), Sta. 0+525 - Sta. 0+707 (L/S), Sta.0+743 - Sta. 0+799 (LS), Sta. 0+555 - Sta. 0+643 (R/S), Sta. 0+682.50 - Sta. 0+799 (R/S), Sta. 2+055 - Sta. 2+617 both side (Downstream), Tigaon, Camarines Sur is a DPWH-tracked public work in TIGAON (CAMARINES SUR), CAMARINES SUR, Region V. Reported contract value: ₱82,025,000.00. Status: Reported complete (DPWH). Contractor on record: PARTIDO CONST & SUPPLY. Figures trace to sumbong.

TIGAON (CAMARINES SUR), CAMARINES SUR, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bicol River, Upstream Bacolod Bridge, Left Side, Sta. 0+147 - Sta. 0+600, Bato, Camarines Sur
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-22-0011213

₱16,995,909.00 · FY2022

Released to Camarines Sur 4th District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002964

₱353,891,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

11 projects · ₱931.9M total · 4 flags

4. Implementation

Contract Amount

₱82,025,000.00

Progress

Reported complete (DPWH)

Start Date

April 5, 2022

Target End

January 29, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.