Buildings and Facilities17DO0106

COMPLETION OF FOUR (4) STOREY TWELVE (12) CLASSROOM SCHOOL BUILDING AT STAND ALONE SHS 9 (EASTWOOD), RODRIGUEZ II EASTWOOD, RODRIGUEZ, RIZAL

COMPLETION OF FOUR (4) STOREY TWELVE (12) CLASSROOM SCHOOL BUILDING AT STAND ALONE SHS 9 (EASTWOOD), RODRIGUEZ II EASTWOOD, RODRIGUEZ, RIZAL is a DPWH-tracked public work in Rizal 2nd DEO, Region IV-A. Reported contract value: ₱1,877,834.17. Status: Reported complete (DPWH). Contractor on record: DARCY. Figures trace to dpwh.

Rizal 2nd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱19,150,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement/Construction of Flood Control Structures along Manggahan River, Rodriguez, Rizal
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0006150

₱67,088.00 · FY2017

Released to Visayas State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,877,834.17

Progress

Reported complete (DPWH)

Start Date

November 2, 2017

Target End

December 1, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.