REPAIR/REHABILITATION (CONCRETE REBLOCKING) ALONG DAANG MAHARLIKA K 209+(-896) - K 210+000, TACTAC SECTION STA. FE, NUEVA VIZCAYA

REPAIR/REHABILITATION (CONCRETE REBLOCKING) ALONG DAANG MAHARLIKA K 209+(-896) - K 210+000, TACTAC SECTION STA. FE, NUEVA VIZCAYA is a DPWH-tracked public work in Nueva Vizcaya 2nd DEO, Region II. Reported contract value: ₱18,512,526.56. Status: Reported complete (DPWH). Contractor on record: J E L CONST. Figures trace to dpwh.

Nueva Vizcaya 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Flood Control and Drainage Structure along Sta. Cruz River, Salinas Section 1, Bambang, Nueva Vizcaya
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-LGRCB-21-0010533

₱263,769.00 · FY2021

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱18,512,526.56

Progress

Reported complete (DPWH)

Start Date

December 23, 2021

Target End

April 21, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.