Construction of Flood Mitigation Structure24BE0097

Construction of Flood Mitigation Structure along Cagayan River, barangay Arusip, City of Ilagan, Isabela

Construction of Flood Mitigation Structure along Cagayan River, barangay Arusip, City of Ilagan, Isabela is a DPWH-tracked public work in ILAGAN CITY (CAPITAL) (ISABELA), ISABELA, Region II. Reported contract value: ₱96,492,518.40. Status: Reported complete (DPWH). Contractor on record: DRAGON TWELVE BUILDERS & CONST SUPPLY. Figures trace to sumbong.

ILAGAN CITY (CAPITAL) (ISABELA), ISABELA, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Cagayan River, Roxas Section, Naguilian, Isabela
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-24-0019638

₱-685,078,986.00 · FY2024

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010519

₱1,921,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0016971

₱1,021,610.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010579

₱177,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

56 projects · ₱4.1B total · 18 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - WIDENING OF PERMANENT BRIDGES - MALALAM BR. (B01121LZ) ALONG MAHARLIKA HIGHWAY

Region II, Region II

2025₱253.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ILAGAN-DIVILACAN ROAD, IL

Region II, Region II

2024₱192.8M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD: BRIDGE - WIDENING OF PERMANENT BRIDGES - ARCON BRIDGE (B01130LZ) ALONG DAANG MAHARLIKA (LZ)

Region II, Region II

2022₱155.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES -CONSTRUCTION OF ILAGAN-DIVILACAN ROAD, P

Isabela 1st DEO, Region II

2025₱144.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF ILAGAN-DIVILACAN ROAD, P

Isabela 1st DEO, Region II

2025₱144.7M
Past target date (DPWH On-Going)

Construction of Slope Protection Works for Cagayan River Basin, Cagayan River, Santa Maria, Isabela

SANTA MARIA (ISABELA), ISABELA, Region II

2024₱144.7M
Reported complete (DPWH)
View all 56 projects →

4. Implementation

Contract Amount

₱96,492,518.40

Progress

Reported complete (DPWH)

Start Date

May 29, 2024

Target End

May 18, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.