Roads22IL0004

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY HINAPU GAMAY - BARANGAY SAN AGUSTIN,

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD, BARANGAY HINAPU GAMAY - BARANGAY SAN AGUSTIN, is a DPWH-tracked public work in Southern Leyte 1st DEO, Region VIII. Reported contract value: ₱4,949,977.72. Status: Reported complete (DPWH). Contractor on record: J'NER CEPADA CONST. Figures trace to dpwh.

Southern Leyte 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Lawigan Flood Control along Jct Himay-angan - Silago - Abuyog - Bdry. Road, St. Bernard, Southern Leyte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-22-0001976

₱171,653,146.00 · FY2022

Released to Southern Leyte 1st DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

41 projects · ₱219.6M total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - BATO-BONTOC RD - K1126+529 - K1126+740, K1128+828 - K1129+609

Southern Leyte 1st DEO, Region VIII

2024₱29.4M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - ROAD WIDENING -SECONDARY ROADS - JCT. PANAN-AWAN AIRPORT RD - K1125+(-321) - K1125+480

Southern Leyte 1st DEO, Region VIII

2025₱28.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONCRETING OF BRGY. LAWGAWAN ROAD, BONTOC, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2022₱11.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES CONCRETING OF BRGY. HINAPU - BRGY. SAN AGUSTIN ROAD, MAASIN CITY, SO

Southern Leyte 1st DEO, Region VIII

2022₱9.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM - MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY CABUL-ANONAN, MALITBOG, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2024₱6.4M
Reported complete (DPWH)
No sat.

REHAB./MAJOR REPAIR OF PERMANENT CONCEPCION BRIDGE ALONG BDRY. SO. LEYTE-MAASIN-MACROHON-SOGOD-DAANG MAHARLIKA (B00317LT), CONCEPCION, MALITBOG, SOUTHERN LEYTE

Southern Leyte 1st DEO, Region VIII

2016₱6.1M
Reported complete (DPWH)
View all 41 projects →

4. Implementation

Contract Amount

₱4,949,977.72

Progress

Reported complete (DPWH)

Start Date

February 10, 2022

Target End

July 9, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.