Roads21PG0030

CONCRETING OF SITIO COCOY TO SITIO ABABBA BARANGAY TUKUCAN FMR, BARANGAY TUKUCAN, TINOC, IFUGAO, TINOC, IFUGAO

CONCRETING OF SITIO COCOY TO SITIO ABABBA BARANGAY TUKUCAN FMR, BARANGAY TUKUCAN, TINOC, IFUGAO, TINOC, IFUGAO is a DPWH-tracked public work in Ifugao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱11,790,939.62. Status: Reported complete (DPWH). Contractor on record: BEGAL DESIGN. Figures trace to dpwh.

Ifugao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱7,260,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Boliwong Flood Control, Lagawe, Ifugao
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-21-0013544

₱-26,000.00 · FY2021

Released to Baliangao School of Fisheries (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

21 projects · ₱155.1M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG IBULAO RIVER, STA. 325+444 - STA. 325+685 AND STA. 332+180 - K0332+350, HAPID, LAMUT, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2024₱29.4M
Past target date (DPWH On-Going)
No sat.

REHAB./RECONS'TN. OF RDS. W/ SLIPS, SLOPE COLLAPSE & LANDSLIDE ALONG KIANGAN-TINOC-BUGUIAS RD. K0341+025-K0341+042,K0341+547-K0347+574,K0344+035-K0344+055,K0344+452-K0344+464, K0346+561-K0346+608,K0347+022-K0347+037,K0348+467-K0348+482,K0349+070-K0349+085

Ifugao 1st DEO, Cordillera Administrative Region

2025₱19.7M
Past target date (DPWH On-Going)
No sat.

OFF-CARRIAGEWAY IMPROVEMENT ALONG NUEVA VIZCAYA-IFUGAO-MT. PROVINCE ROAD - K0298 + 450 - K0298 884, K0323+300 K0323+357, K0325+769-K0325+919, K0326+000-K0326+104, K0326+169-K0326+419, K0326+552 -K0326+765, K0326+812-K0326+930, K0326+970-K0327+092, K0327+

Ifugao 1st DEO, Cordillera Administrative Region

2022₱19.2M
Reported complete (DPWH)
No sat.

REPAIR/REHABILITATION ALONG KIANGAN-TINOC-BUGUIAS ROAD, K0328+800 - K0328+950, JULONGAN, KIANGAN, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2022₱19.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ROAD BARANGAY BAGUINGUE, KIANGAN, IFUGAO, BAGUINGE, KIANGAN, IFUGAO

Ifugao 1st DEO, Cordillera Administrative Region

2023₱7.9M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-WATER MANAGEMENT FACILITIES-WATER SUPPLY-LOCAL INFRASTRUCTURE PROGRAM- IMPROVEMENT AND CONSTRUCTION OF WATER SYSTEM AT BRGY. CABUAAN, BAYOMBONG, NUEVA VIZCAYA

Nueva Vizcaya DEO, Region II

2020₱5.0M
Reported complete (DPWH)
View all 21 projects →

4. Implementation

Contract Amount

₱11,790,939.62

Progress

Reported complete (DPWH)

Start Date

August 18, 2021

Target End

January 14, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.