Buildings and Facilities24HN0087

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, DPWH CEBU 6TH DEO QA LABORATORY BUILDING, MANDAUE CITY, CEBU

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, DPWH CEBU 6TH DEO QA LABORATORY BUILDING, MANDAUE CITY, CEBU is a DPWH-tracked public work in Cebu 6th DEO, Region VII. Reported contract value: ₱9,849,888.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST. Figures trace to dpwh.

Cebu 6th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Gate at Basak Creek, Lapu - Lapu City, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-24-0011737

₱57,620,507.20 · FY2024

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24HN0087

₱9,849,888.00 · QUIRANTE CONSTRUCTION

Contractor

B

409 projects · ₱18.8B total · 42 flags

Other projects by this contractor

No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF COASTAL ROAD, PHASE 1, BARANGAY IBO, LAPULAPU CITY, CEBU

Region VII, Region VII

2024₱231.5M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TIPOLO RIVER, PHASE 4, MANDAUE CITY

Region VII, Region VII

2025₱202.5M
Past target date (DPWH On-Going)
No sat.

CSSP, BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF MANTAYUPAN ROAD (LEADING TO BANGAG LAPOS CAVE), BARILI, CEBU

Region VII, Region VII

2024₱178.2M
Past target date (DPWH On-Going)
No sat.

OO 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROG, CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONST OF FLOOD CONTROL STRUCTURE ALONG MANANGA RIVER (UPSTREAM), TALISAY CITY, CEBU

Region VII, Region VII

2024₱173.7M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF BABAG-BASAK-SUBABASBAS BYPASS ROAD, LAPU-LAPU CITY

Region VII, Region VII

2024₱173.7M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF MARIGONDON-BASAK BYPASS ROAD, LAPU-LAPU CITY, CEBU

Region VII, Region VII

2024₱173.6M
Past target date (DPWH On-Going)
View all 409 projects →

4. Implementation

Contract Amount

₱9,849,888.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 27, 2024

Target End

September 10, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.