Buildings and Facilities17RD0111

CONSTRUCTION OF ONE (1) UNIT ONE (1) STOREY THREE (3) CLASSROOMS AT BULATA ES, CAUAYAN, NEG. OCC.

CONSTRUCTION OF ONE (1) UNIT ONE (1) STOREY THREE (3) CLASSROOMS AT BULATA ES, CAUAYAN, NEG. OCC. is a DPWH-tracked public work in Negros Occidental 3rd DEO, Negros Island Region. Reported contract value: ₱4,346,097.93. Status: Reported complete (DPWH). Contractor on record: RHT CONST AND SUPPLIES. Figures trace to dpwh.

Negros Occidental 3rd DEO, Negros Island Region
Region: Negros Island Region

Follow the peso

3 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2017 · ₱5,000

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROXI-17-0013047 · ₱1,689,987

    Possible match · score 0.68

    DBM release source ↗
  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2010-04-19 → 2020-12-22

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Unit-cost benchmark · School building, cost per classroom (new school building)

₱1,448,699 per classroom= 1.0x the Negros Island Region median (n=274)

Contract cost ₱4,346,098 ÷ 3 classroom read from the DPWH title (“THREE (3) CLASSROOMS”; classroom count in title). National percentile: 37. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project near Taongan River, Barangay Gil Montilla, Sipalay City, Negros Occidental
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0013047

₱1,689,987.00 · FY2017

Released to Division of Panabo Mo City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,346,097.93

Progress

Reported complete (DPWH)

Start Date

November 16, 2017

Target End

February 18, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.