Roads24JJ0017

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2031 + 1005 - K2032 +000, K2032 + 734 - K2032 + 757, K2033 + 058 - K2033 + 074, K2035 + 105 - K2035 + 122

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2031 + 1005 - K2032 +000, K2032 + 734 - K2032 + 757, K2033 + 058 - K2033 + 074, K2035 + 105 - K2035 + 122 is a DPWH-tracked public work in Zamboanga del Norte 4th DEO, Region IX. Reported contract value: ₱24,500,000.00. Status: Reported complete (DPWH). Contractor on record: DAB CONST. Figures trace to dpwh.

Zamboanga del Norte 4th DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱31,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Poblacion, Polanco, Zamboanga del Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-24-0017205

₱988,371,108.00 · FY2024

Released to Zamboanga del Norte 4th DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

10 projects · ₱141.0M total · 0 flags

4. Implementation

Contract Amount

₱24,500,000.00

Progress

Reported complete (DPWH)

Start Date

March 27, 2024

Target End

December 5, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.