GAA 2024 SSP24JA0085

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT MAMPANG NHS, BARANGAY MAMPANG, ZAMBOANGA CITY

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT MAMPANG NHS, BARANGAY MAMPANG, ZAMBOANGA CITY is a DPWH-tracked public work in Zamboanga City 2nd DEO, Region IX. Reported contract value: ₱14,694,391.43. Status: Past target date (DPWH On-Going). Contractor on record: DAB CONST. Figures trace to dpwh.

Zamboanga City 2nd DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Patalon, Zamboanga City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Zamboanga City 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

10 projects · ₱141.0M total · 0 flags

Other projects by this contractor

No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF SABO DAM UPSTREAM OF DIVERSION WORKS, VITALI CIS, SIBULAO, ZAMBOANGA CITY

Zamboanga City 2nd DEO, Region IX

2025₱28.2M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2031 + 1005 - K2032 +000, K2032 + 734 - K2032 + 757, K2033 + 058 - K2033 + 074, K2035 + 105 - K2035 + 122

Zamboanga del Norte 4th DEO, Region IX

2024₱24.5M
Reported complete (DPWH)
No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2140 + 301 - K2140 + 334, K2143 + 326 -K2143 + 352, K2143 + 478 - K2143 + 518

Zamboanga del Norte 4th DEO, Region IX

2025₱23.8M
Past target date (DPWH On-Going)
No sat.

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2112 + 440 - K2112 + 500, K2119 + 149 - K2119 + 192, K2120 + 075 - K2120 + 105

Zamboanga del Norte 4th DEO, Region IX

2025₱15.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT CURUAN NHS, BARANGAY CURUAN, ZAMBOANGA CITY

Zamboanga City 2nd DEO, Region IX

2024₱14.7M
Past target date (DPWH On-Going)
No sat.

REHABILITATION OF MULTI-PURPOSE BUILDING (MUNICIPAL GYM), KALAWIT, ZAMBOANGA DEL NORTE

Zamboanga del Norte 3rd DEO, Region IX

2025₱5.9M
Reported complete (DPWH)
View all 10 projects →

4. Implementation

Contract Amount

₱14,694,391.43

Progress

Past target date (DPWH On-Going)

Start Date

May 30, 2024

Target End

January 4, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.