Roads24HM0037

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD IN BARANGAY OLAVE, ENRIQUE VILLANUEVA, SIQUIJO

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD IN BARANGAY OLAVE, ENRIQUE VILLANUEVA, SIQUIJO is a DPWH-tracked public work in Siquijor DEO, Negros Island Region. Reported contract value: ₱4,796,373.25. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: JCJD PREMIER BUILDERS CORP. Figures trace to dpwh.

Siquijor DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure in Barangay Caipilan, Siquijor, Siquijor
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-24-0006016

₱39,000.00 · FY2024

Released to Barayong National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

7 projects · ₱84.1M total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, SIQUIJOR CIRCUMFERENTIAL RD - K0070+000 - K0070+663

Siquijor DEO, Negros Island Region

2024₱22.4M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, SIQUIJOR CIRCUMFERENTIAL RD - K0071+000 - K0071+648

Siquijor DEO, Negros Island Region

2024₱22.4M
Past target date (DPWH On-Going)
No sat.

CAPITAL OUTLAY - BASIC EDUCATIONAL FACILITIES FUND (BEFF) - BATCH 2: CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS UNDER THE DEPED'S BASIC EDUCATIONAL FACILITIES FUNDS: CONSTRUCTION OF 2STY6CL, SAN JUAN INTEGRATED SCHOOL, SAN JUAN, SIQUIJOR

Siquijor DEO, Negros Island Region

2022₱21.0M
Past target date (DPWH On-Going)
No sat.

CSSP: BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, PIT-OS-CABANGAHAN ROAD, BARANGAY PIT-OS, CEBU CITY, CEBU

Region VII, Region VII

2025₱9.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING IN BARANGAY LOMANGCAPAN, ENRIQUE VILLANUEVA, SIQUIJOR

Siquijor DEO, Negros Island Region

2024₱1.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE (EVACUATION CENTER) BUILDING IN BARANGAY PISONG B, MARIA, SIQUIJOR

Siquijor DEO, Negros Island Region

2024₱1.9M
Reported complete (100% progress, DPWH status On-Going)
View all 7 projects →

4. Implementation

Contract Amount

₱4,796,373.25

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 14, 2024

Target End

April 9, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.