Construction of Slope Protection Structure22CI0065

Construction of Reinforced Concrete Slope Protection along Taug River, Angeles City, Pampanga Sta. 0+600 to Sta. 1+350 (L/D)

Construction of Reinforced Concrete Slope Protection along Taug River, Angeles City, Pampanga Sta. 0+600 to Sta. 1+350 (L/D) is a DPWH-tracked public work in ANGELES CITY (PAMPANGA), PAMPANGA, Region III. Reported contract value: ₱70,651,739.38. Status: Reported complete (DPWH). Contractor on record: STRONGLANE BUILDERS AND TRADING CORP FORMERLY: STRONGLANE CONST & TRADING. Figures trace to sumbong.

ANGELES CITY (PAMPANGA), PAMPANGA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Gumain River, Cabangcalan Section, Barangay Cabangcalan, Floridablanca, Pampanga
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-22-0010043

₱47,413.00 · FY2022

Released to Davao Occidental District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0012252

₱1,104,074.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0002420

₱749,061.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0010260

₱254,906.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002914

₱723,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0002421

₱71,763.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0005826

₱46,080.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0004169

₱110,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001629

₱159,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

20 projects · ₱876.9M total · 5 flags

4. Implementation

Contract Amount

₱70,651,739.38

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

October 27, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.