Construction of Revetment22OC0014

Construction of Groundsill / Revetment wall along Makati Diversion Channel (Phase 2), Barangay San Lorenzo, Makati City

Construction of Groundsill / Revetment wall along Makati Diversion Channel (Phase 2), Barangay San Lorenzo, Makati City is a DPWH-tracked public work in CITY OF MAKATI (METROPOLITAN MANILA), MAKATI CITY, National Capital Region. Reported contract value: ₱49,500,000.00. Status: Reported complete (DPWH). Contractor on record: STRONGLANE BUILDERS AND TRADING CORP FORMERLY: STRONGLANE CONST & TRADING. Figures trace to sumbong.

CITY OF MAKATI (METROPOLITAN MANILA), MAKATI CITY, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along the Banks of Creeks, Brgy. 166 (Phase 2), Caloocan City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003128

₱703,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003020

₱287,986,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001728

₱75,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0007225

₱945,393.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-NCR-22-0009235

₱270,626.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱49,500,000.00

Progress

Reported complete (DPWH)

Start Date

March 22, 2022

Target End

May 28, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.