Roads25OG0109

PREVENTIVE MAINTENANCE - TERTIARY ROADS: QUEZON AVENUE (S05206LZ) - K0009 + 340 - K0010 + 000, QUEZON CITY

PREVENTIVE MAINTENANCE - TERTIARY ROADS: QUEZON AVENUE (S05206LZ) - K0009 + 340 - K0010 + 000, QUEZON CITY is a DPWH-tracked public work in Quezon City 2nd DEO, National Capital Region. Reported contract value: ₱7,419,066.95. Status: Past target date (DPWH On-Going). Contractor on record: WAY MAKER GEN CONTRACTOR OPC. Figures trace to dpwh.

Quezon City 2nd DEO, National Capital Region
Region: National Capital Region

Satellite images pending: this project is in the imagery queue (completed projects first, then ongoing). Before/after images will appear here when it is processed.

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2025 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROXIII-25-0014134 · ₱21,245,000 · release to the district office, not itemized per project

    Possible match · score 0.59

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25OG0109 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    0% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Road, cost per km (preventive maintenance / overlay)

₱11,241,011 per km= 0.4x the National Capital Region median (n=177)

Contract cost ₱7,419,067 ÷ 0.66 km read from the DPWH title (“K0009 + 340 - K0010 + 000”; K-post / station range length). National percentile: 15. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: PREVENTIVE MAINTENANCE - TERTIARY ROADS: QUEZON AVENUE (S05206LZ) - K0009 + 340 - K0010 + 000, QUEZON CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Marikina River, Phase 2, Barangay Bagumbayan, Quezon City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-25-0014134

₱21,245,000.00 · FY2025

Released to Division of Butuan City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱7,419,066.95

Progress

Past target date (DPWH On-Going)

Start Date

March 25, 2025

Target End

April 21, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.