Flood Control and Drainage25CD0076

REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG MARILAO RIVER, SAOG - LAMBAKIN SECTION, STA. 08+600 - STA. 08+860, MARILAO, BULACAN

REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG MARILAO RIVER, SAOG - LAMBAKIN SECTION, STA. 08+600 - STA. 08+860, MARILAO, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱47,528,956.74. Status: Past target date (DPWH On-Going). Contractor on record: A C SOLIVEN CONST. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 94%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure along Marilao River, Saog-Lambakin Section, Sta. 08+600 - Sta. 08+860, Marilao, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-25-0007502

₱7,279,122.00 · FY2025

Released to Surigao del Norte State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱47,528,956.74

Progress

Past target date (DPWH On-Going)

Start Date

February 20, 2025

Target End

August 22, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.