Roads21DN0044

IMPROVEMENT/UPGRADING OF HIGHWAY 2000 (PHASE 2) TAYTAY, RIZAL

IMPROVEMENT/UPGRADING OF HIGHWAY 2000 (PHASE 2) TAYTAY, RIZAL is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱28,806,030.00. Status: Reported complete (DPWH). Contractor on record: HONY TRADING. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱1,987,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Ilog Pugad Creek, Taytay, Rizal
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱911,537,000.00 · FY2021

Released to Rizal 1st District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

137 projects · ₱3.1B total · 0 flags

4. Implementation

Contract Amount

₱28,806,030.00

Progress

Reported complete (DPWH)

Start Date

February 15, 2021

Target End

September 12, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.