Roads22AI0065

CONSTRUCTION OF PEDESTRIAN OVERPASS, BINALONAN, PANGASINAN

CONSTRUCTION OF PEDESTRIAN OVERPASS, BINALONAN, PANGASINAN is a DPWH-tracked public work in Pangasinan 3rd DEO, Region I. Reported contract value: ₱19,502,704.17. Status: Reported complete (DPWH). Contractor on record: KEVIN PAUL CONST. Figures trace to dpwh.

Pangasinan 3rd DEO, Region I
Region: Region I

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2022 · ₱45,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROXI-22-0002016 · ₱16,994,708 · release to the district office, not itemized per project

    Possible match · score 0.69

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 22AI0065 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2021-11-06 → 2025-08-04

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF PEDESTRIAN OVERPASS, BINALONAN, PANGASINAN

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tagamusing River, Sta. 0+000 + Sta. 266.40, Brgy. Poblacion, Binalonan, Pangasinan (Package 9)
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-22-0002016

₱16,994,708.00 · FY2022

Released to Davao City District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱19,502,704.17

Progress

Reported complete (DPWH)

Start Date

February 27, 2022

Target End

August 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.