Bridges16B00072

BRIDGE CONSTRUCTION/REPLACEMENT PROGRAM (BRCP) I IN LUZON: (DESIGN AND BUILD SCHEME) PHASE 2, KONGKONG BRIDGE AND APPROACHES ALONG BAMBANG-KASIBU-SOLANO ROAD, KASIBU, NUEVA VIZCAYA

BRIDGE CONSTRUCTION/REPLACEMENT PROGRAM (BRCP) I IN LUZON: (DESIGN AND BUILD SCHEME) PHASE 2, KONGKONG BRIDGE AND APPROACHES ALONG BAMBANG-KASIBU-SOLANO ROAD, KASIBU, NUEVA VIZCAYA is a DPWH-tracked public work in Region II, Region II. Reported contract value: ₱7,019,442.50. Status: Reported complete (DPWH). Contractor on record: NORTHERN BUILDERS. Figures trace to dpwh.

Region II, Region II
Region: Region II

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱7,019,442.50

Progress

Reported complete (DPWH)

Start Date

August 18, 2017

Target End

November 14, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.