Roads23L00200

INSTALLATION OF ROAD SAFETY FACILITIES ALONG DIGOS - MAKAR ROAD, DAVAO DEL SUR - K1572+006 - K1572+100, K1573+124.757 - K1576+349, K1577+297 - K1580+586, K1581+419 - K1583+540

INSTALLATION OF ROAD SAFETY FACILITIES ALONG DIGOS - MAKAR ROAD, DAVAO DEL SUR - K1572+006 - K1572+100, K1573+124.757 - K1576+349, K1577+297 - K1580+586, K1581+419 - K1583+540 is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱133,724,888.86. Status: Past target date (DPWH On-Going). Contractor on record: VICENTE T LAO CONST. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

407 projects · ₱34.7B total · 2 flags

4. Implementation

Contract Amount

₱133,724,888.86

Progress

Past target date (DPWH On-Going)

Start Date

August 17, 2023

Target End

April 22, 2024

5. Audit