Bridges, Roads18K00150

CONST. OF BYPASS/DIVERSION ROADS,MANOLO FORTICH-MIS. OR./ALTERNATE BYPASS RD.INCL.ROW & BRIDGE, BUK

CONST. OF BYPASS/DIVERSION ROADS,MANOLO FORTICH-MIS. OR./ALTERNATE BYPASS RD.INCL.ROW & BRIDGE, BUK is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱138,758,218.18. Status: Reported complete (DPWH). Contractor on record: EQUI-PARCO CONST CO. Figures trace to dpwh.

Region X, Region X
Region: Region X

Follow the peso

1 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    Not yet linked

  2. 2. SARO / NCA release

    Not yet linked

  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    100% reported · imagery 2014-03-02 → 2025-09-28

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2018 GAA. DBM GAA FY2018

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

725 projects · ₱77.9B total · 5 flags

4. Implementation

Contract Amount

₱138,758,218.18

Progress

Reported complete (DPWH)

Start Date

July 23, 2018

Target End

October 25, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.