Construction of Flood Mitigation Structure24HJ0063

Construction of Flood Control along McKinley River, Guihulngan City, Negros Oriental

Construction of Flood Control along McKinley River, Guihulngan City, Negros Oriental is a DPWH-tracked public work in CITY OF GUIHULNGAN (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VII. Reported contract value: ₱14,700,000.00. Status: Reported complete (DPWH). Contractor on record: EJJ CONST AND SUPPLY. Figures trace to sumbong.

CITY OF GUIHULNGAN (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along McKinley River, Guihulngan City, Negros Oriental
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-D-24-0014212

₱2,977,141.00 · FY2024

Released to Regional Office - I (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0007805

₱1,487,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0002591

₱233,883.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0007808

₱137,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

28 projects · ₱166.9M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - CONSTRUCTION OF NEW BRIDGES MABATO BR. 2 ALONG MABINAY - AYUNGON ROAD, AYUNGON, NEGROS ORIENTAL

Negros Oriental 1st DEO, Negros Island Region

2025₱29.4M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES IMPROVEMENT OF BARANGAY BANBAN-NABHANG-CAR

Negros Oriental 1st DEO, Negros Island Region

2025₱24.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION OF ACCESS ROAD, BRGY. UBAY, PULUPANDAN, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2023₱9.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - BRGY. MANTAHAW - MOLOGPOLOG - NALUND

Negros Oriental 1st DEO, Negros Island Region

2023₱9.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BARANGAY MANTAHAW-MOLOGPOL

Negros Oriental 1st DEO, Negros Island Region

2025₱9.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CABAGNAAN, LA CASTELLANA, NEGROS OCCIDENTAL

Negros Occidental 2nd DEO, Negros Island Region

2024₱5.9M
Reported complete (DPWH)
View all 28 projects →

4. Implementation

Contract Amount

₱14,700,000.00

Progress

Reported complete (DPWH)

Start Date

February 7, 2024

Target End

August 5, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.