Buildings and Facilities18IF0185

CY 2018 BASIC EDUCATIONAL FACILITIES FUND (BEFF), CONSTRUCTION OF CLASSROOMS, BATCH 3, BILWANG NATIONAL HIGH SCHOOL, ISABEL, LEYTE

CY 2018 BASIC EDUCATIONAL FACILITIES FUND (BEFF), CONSTRUCTION OF CLASSROOMS, BATCH 3, BILWANG NATIONAL HIGH SCHOOL, ISABEL, LEYTE is a DPWH-tracked public work in Leyte 4th DEO, Region VIII. Reported contract value: ₱17,725,996.38. Status: Reported complete (DPWH). Contractor on record: ROLANDO M VILLASENCIO CONST. Figures trace to dpwh.

Leyte 4th DEO, Region VIII
Region: Region VIII

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱40,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROVIII-18-0003815 · ₱482,159 · release to the district office, not itemized per project

    Possible match · score 0.77

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱17,725,996 · ROLANDO M VILLASENCIO CONSTRUCTION & GENERAL SERVICES

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-12-04 → 2025-10-31

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CY 2018 BASIC EDUCATIONAL FACILITIES FUND (BEFF), CONSTRUCTION OF CLASSROOMS, BATCH 3, BILWANG NATIONAL HIGH SCHOOL, ISABEL, LEYTE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Matlang, Isabel, Leyte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-18-0003815

₱482,159.00 · FY2018

Released to Division of Southern (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

18IF0185-BILWANG NHS (readv)

₱17,725,996.38 · ROLANDO M VILLASENCIO CONSTRUCTION & GENERAL SERVICES

Award / contract ref: 18IF0185 READV

Contractor

A

37 projects · ₱202.2M total · 0 flags

4. Implementation

Contract Amount

₱17,725,996.38

Progress

Reported complete (DPWH)

Start Date

December 26, 2018

Target End

May 14, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.