Flood Control and Drainage24CL0028

CONSTRUCTION OF SLOPE PROTECTION ALONG BUCAO RIVER, DOWNSTREAM, NORTH APPROACH, BOTOLAN, ZAMBALES, PHASE V

CONSTRUCTION OF SLOPE PROTECTION ALONG BUCAO RIVER, DOWNSTREAM, NORTH APPROACH, BOTOLAN, ZAMBALES, PHASE V is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱96,498,298.75. Status: Past target date (DPWH On-Going). Contractor on record: YPR GEN CONTRACTOR AND CONST SUPPLY INC. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control / Slope Protection Works along Sto. Niño Creek, Capayawan, Botolan, Zambales
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVB-24-0008180

₱217,502.00 · FY2024

Released to President Diosdado Macapagal Memorial National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

217 projects · ₱8.6B total · 22 flags

Other projects by this contractor

Construction of River Control Structure along Pagpagoha River, Upstream, Tablas Island, Romblon

SAN ANDRES (ROMBLON), ROMBLON, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRUCTURE, TINGARAY RIVER, UPSTREAM R/S, BRGY. POBLACION, FERROL, ROMBLON

Region IV-B, Region IV-B

2025₱247.5M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRTUCTURE, TINGARAY

Region IV-B, Region IV-B

2025₱247.5M
Past target date (DPWH On-Going)

Construction of Shore Protection and Coastal Road Development along Barangay Mulawin, Sta. Cruz, Occidental Mindoro

SANTA CRUZ (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B

2023₱241.2M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF CAUSEWAY ALONG BRGY. AMBULONG SECTION, MAGDIWANG, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2024₱236.4M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. ADELA, SAN JOSE, OCC. MINDORO

Region IV-B, Region IV-B

2024₱232.4M
Past target date (DPWH On-Going)
View all 217 projects →

4. Implementation

Contract Amount

₱96,498,298.75

Progress

Past target date (DPWH On-Going)

Start Date

February 16, 2024

Target End

January 10, 2025