Buildings: Construction - without Piles - Low Rise - Concrete (Frame) (1 to 5 Storeys)25DM0187No coordinates published by DPWH

CONSTRUCTION OF CLASSROOMS, ABUYON NHS, SAN NARCISO, QUEZON

CONSTRUCTION OF CLASSROOMS, ABUYON NHS, SAN NARCISO, QUEZON is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱0.00. Status: Ongoing (DPWH-reported) (For Procurement (DPWH-reported)). Contractor on record: Contractor not linked in this database. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A

DPWH did not publish coordinates for this project, so it cannot be placed on the map or checked with satellite images.

Region: Region IV-A

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2025 · ₱5,000 (shared by many projects, not this project's own line)

    Possible match · score 0.83

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROXIII-25-0010033 · ₱4,550,308 · release to the district office, not itemized per project

    Possible match · score 0.58

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25DM0187 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    0% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF CLASSROOMS, ABUYON NHS, SAN NARCISO, QUEZON

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Project at San Roque-Taquico, Sampaloc, Quezon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-25-0010033

₱4,550,308.00 · FY2025

Released to Division of Siargao (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱0.00

Progress

For Procurement (DPWH-reported)

Start Date

DPWH didn't publish a start date · Source: DPWH Transparency Portal

Target End

DPWH didn't publish a target completion date · Source: DPWH Transparency Portal

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.