Rehabilitation / Major Repair of Drainage Structure24CM0028

Improvement of Drainage Outfall System connecting National Highway, San Juan, Castillejos Zambales

Improvement of Drainage Outfall System connecting National Highway, San Juan, Castillejos Zambales is a DPWH-tracked public work in CASTILLEJOS (ZAMBALES), ZAMBALES, Region III. Reported contract value: ₱19,599,347.92. Status: Reported complete (DPWH). Contractor on record: M V GUBALLA CONST CORP FORMERLY: M V GUBALLA CONST. Figures trace to sumbong.

CASTILLEJOS (ZAMBALES), ZAMBALES, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Omaya River, San Narciso, Zambales ( Phase 1 )
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-24-0013661

₱256,000.00 · FY2024

Released to Davao City District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0004300

₱30,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007116

₱1,174,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007118

₱108,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

36 projects · ₱260.8M total · 0 flags

4. Implementation

Contract Amount

₱19,599,347.92

Progress

Reported complete (DPWH)

Start Date

February 16, 2024

Target End

February 24, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.