GAA 2025 SSP25KN0059

CONSTRUCTION OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX) IN CITY OF VALENCIA, BUKIDNON

CONSTRUCTION OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX) IN CITY OF VALENCIA, BUKIDNON is a DPWH-tracked public work in Bukidnon 4th DEO, Region X. Reported contract value: ₱4,849,103.01. Status: Past target date (DPWH On-Going). Contractor on record: JRTP CONST. Figures trace to dpwh.

Bukidnon 4th DEO, Region X
Region: Region X

Satellite images pending: this project is in the imagery queue (completed projects first, then ongoing). Before/after images will appear here when it is processed.

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2025 · ₱25,000 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROIII-25-0003247 · ₱182,153 · release to the district office, not itemized per project

    Possible match · score 0.56

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱4,849,103

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    5% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX) IN CITY OF VALENCIA, BUKIDNON

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Barangay Miglamin, Malaybalay City, Bukidnon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-25-0003247

₱182,153.00 · FY2025

Released to Division of Pampanga (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,849,103.01

Progress

Past target date (DPWH On-Going)

Start Date

May 23, 2025

Target End

February 14, 2026