Roads19HA0070

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - JCT. SIKATUNA - BALILIHAN ROAD - BADIANG - CAMBUAC NORTE LEADING TO CAWASAN FALLS AND LAHUG CAVE, SIKATUNA, BOHOL

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS - JCT. SIKATUNA - BALILIHAN ROAD - BADIANG - CAMBUAC NORTE LEADING TO CAWASAN FALLS AND LAHUG CAVE, SIKATUNA, BOHOL is a DPWH-tracked public work in Bohol 1st DEO, Region VII. Reported contract value: ₱9,408,000.00. Status: Reported complete (DPWH). Contractor on record: WYNN CONST AND DEVELOPMENT CORP FORMERLY: WYNN CONST. Figures trace to dpwh.

Bohol 1st DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVII-19-0011352

₱9,308,000.00 · FY2019

Released to Sikatuna National Agricultural High Sch (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

70 projects · ₱883.7M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROAD LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - SAN ROQUE-BOCTOL-BAUCAN TO DATAG NORTE ROAD CONNECTING BALILIHAN-HANOPOL-BATUAN

Bohol 1st DEO, Region VII

2025₱67.4M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES - SAN ROQUE-BOCTOL-BAUCAN TO DATAG NORTE ROAD CONNECTING BALILIHAN-HANOPOL-BATUAN ROAD AND CORTES-BALILIHAN-CATIGBIAN-MACAAS ROAD IN SUPPORT TO THE FURNITURE, GIFTS

Bohol 1st DEO, Region VII

2023₱62.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRTEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF POBLACION NORTE - BEHIND

Bohol 3rd DEO, Region VII

2022₱49.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF SAN ROQUE-BOCTOL-BAUCAN

Region VII, Region VII

2023₱48.2M
Reported complete (DPWH)
No sat.

OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - JCT (TNR) CORTES-BALILIHAN-CATIGBIAN-MACAAS RD - K0023+000 - K0025+000, K0030+300 - K0030+429

Bohol 1st DEO, Region VII

2022₱40.8M
Reported complete (DPWH)
No sat.

REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - PANGLAO ISLAND CIRCUMFERENTIAL RD - K0001 + (-987) - K0001+(-451), K0001+120 - K0001+858

Bohol 1st DEO, Region VII

2024₱37.2M
Reported complete (DPWH)
View all 70 projects →

4. Implementation

Contract Amount

₱9,408,000.00

Progress

Reported complete (DPWH)

Start Date

June 11, 2019

Target End

August 4, 2019

5. Audit