GAA 2025 DEPED BEFF25BC0086

CONSTRUCTION OF 1 STOREY 2 CLASSROOM WITH CR AT ALINUNU ELEMENTARY SCHOOL ABULUG, CAGAYAN

CONSTRUCTION OF 1 STOREY 2 CLASSROOM WITH CR AT ALINUNU ELEMENTARY SCHOOL ABULUG, CAGAYAN is a DPWH-tracked public work in Cagayan 2nd DEO, Region II. Reported contract value: ₱4,934,746.95. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: OLIVA DESIGN AND CONST. Figures trace to dpwh.

Cagayan 2nd DEO, Region II
Region: Region II

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2025 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROV-25-0015542 · ₱4,746,264 · release to the district office, not itemized per project

    Possible match · score 0.70

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱4,934,747 · OLIVA DESIGN AND CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2024-09-24 → 2024-09-24

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · School building, cost per classroom (new school building)

₱2,467,373 per classroom= 1.9x the Region II median (n=370)

Contract cost ₱4,934,747 ÷ 2 classroom read from the DPWH title (“2 CLASSROOM”; classroom count in title). National percentile: 80. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF 1 STOREY 2 CLASSROOM WITH CR AT ALINUNU ELEMENTARY SCHOOL ABULUG, CAGAYAN

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Alannay Flood Control Structure along Zinundungan River, Lasam, Cagayan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-25-0015542

₱4,746,264.00 · FY2025

Released to Division of Albay (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

25BC0086-Construction of 1 Storey 2 Classroom with

₱4,934,746.95 · OLIVA DESIGN AND CONSTRUCTION

Contractor

78 projects · ₱696.5M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF SANCHEZ MIRA FLOOD STRUCTURE A

Cagayan 2nd DEO, Region II

2025₱72.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING (NORTHWESTERN CAGAYAN GENERAL HOSPITAL) PACKAGE 2, PINILI, ABULUG, CAGAYAN

Cagayan 2nd DEO, Region II

2023₱49.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING (NORTHWESTERN CAGAYAN GENERAL HOSPITAL), PINILI, ABULUG, CAGAYAN

Cagayan 2nd DEO, Region II

2023₱49.5M
Reported complete (DPWH)
No sat.

CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-ABULUG-BALLESTEROS BAY VIEW BOULEVARD INCLUDING ACCESS ROAD LEADING TO BEACH RESORTS, ABULUG, CAGAYAN (PHASE 4)

Cagayan 2nd DEO, Region II

2022₱29.1M
Reported complete (DPWH)
No sat.

CSSP- BASIC INFRASTRUCTURE PROGRAM (BIP)-EVACUATION CENTERS / QUARANTINE FACILITIES / PUBLIC HEALTH FACILITIES-COUNSTRUCTION OF MULTI-PURPOSE BUILDING (NORTHWESTERN CAGAYAN GENERAL HOSPITAL), BRGY. PINILI, ABULUG, CAGAYAN

Cagayan 2nd DEO, Region II

2023₱24.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM- ROLL-IT) STO. TOMAS BARANGAY ROAD LEADING TO MANI

Cagayan 2nd DEO, Region II

2024₱24.5M
Reported complete (DPWH)
View all 78 projects →

4. Implementation

Contract Amount

₱4,934,746.95

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

June 5, 2025

Target End

September 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.