Buildings and Facilities22OH0059

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 867,PANDACAN, MANILA

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 867,PANDACAN, MANILA is a DPWH-tracked public work in South Manila DEO, National Capital Region. Reported contract value: ₱9,797,851.50. Status: Reported complete (DPWH). Contractor on record: YPR GEN CONTRACTOR AND CONST SUPPLY INC. Figures trace to dpwh.

South Manila DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 77%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures and Facilities along Earnshaw St., (Estero de San Miguel to A.H. Lacson Ave.) and Antipolo St., (G. Tuazon to Espana Blvd.), Manila City
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXII-22-0000752

₱12,780,000.00 · FY2022

Released to SOCCSKSARGEN General Hospital (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

217 projects · ₱8.6B total · 22 flags

Other projects by this contractor

Construction of River Control Structure along Pagpagoha River, Upstream, Tablas Island, Romblon

SAN ANDRES (ROMBLON), ROMBLON, Region IV-B

2024₱289.5M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRUCTURE, TINGARAY RIVER, UPSTREAM R/S, BRGY. POBLACION, FERROL, ROMBLON

Region IV-B, Region IV-B

2025₱247.5M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES- CONST. OF FLOOD MITIGATING STRTUCTURE, TINGARAY

Region IV-B, Region IV-B

2025₱247.5M
Past target date (DPWH On-Going)

Construction of Shore Protection and Coastal Road Development along Barangay Mulawin, Sta. Cruz, Occidental Mindoro

SANTA CRUZ (OCCIDENTAL MINDORO), OCCIDENTAL MINDORO, Region IV-B

2023₱241.2M
Reported complete (DPWH)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONST. OF CAUSEWAY ALONG BRGY. AMBULONG SECTION, MAGDIWANG, SIBUYAN ISLAND, ROMBLON

Region IV-B, Region IV-B

2024₱236.4M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE ALONG BUSUANGA RIVER, BRGY. ADELA, SAN JOSE, OCC. MINDORO

Region IV-B, Region IV-B

2024₱232.4M
Past target date (DPWH On-Going)
View all 217 projects →

4. Implementation

Contract Amount

₱9,797,851.50

Progress

Reported complete (DPWH)

Start Date

June 8, 2022

Target End

November 4, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.