Roads18DM0039

CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - SN FRANCISCO - SN ANDRES SN NARCISO RD - K0371+400 - K0372+300, K0372+600 - K0373+000, K0387+433 - K0387+888, K0388+276 - K0388+730, K0391+000 - K0391+896, SAN NARCISO - SAN ANDRES SECTION

CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - SN FRANCISCO - SN ANDRES SN NARCISO RD - K0371+400 - K0372+300, K0372+600 - K0373+000, K0387+433 - K0387+888, K0388+276 - K0388+730, K0391+000 - K0391+896, SAN NARCISO - SAN ANDRES SECTION is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱39,200,000.00. Status: Reported complete (DPWH). Contractor on record: RAPID FOREMOST CONST CO. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Hingoso River, San Isidro Ibaba-San Vicente Section, General Luna, Quezon
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0032863

₱0.00 · FY2018

Released to San Roque National High Ro School (Kapitangan National High School Annex-San Roque) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction of Drainage Structure along Road – Sn

₱38,417,182.62 · RAPID FOREMOST CONST. .

Contractor

A

314 projects · ₱9.5B total · 3 flags

Other projects by this contractor

View all 314 projects →

4. Implementation

Contract Amount

₱39,200,000.00

Progress

Reported complete (DPWH)

Start Date

February 9, 2018

Target End

November 5, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.