Roads22FC0249

CONSTRUCTION OF BRGY. SAN ANTONIO TO BRGY. LUGUI FMR, BRGY. SAN ANTONIO, LABO, CAMARINES NORTE

CONSTRUCTION OF BRGY. SAN ANTONIO TO BRGY. LUGUI FMR, BRGY. SAN ANTONIO, LABO, CAMARINES NORTE is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱11,582,097.10. Status: Reported complete (DPWH). Contractor on record: GREAT WALL ENGINEERING. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Brgy. Mabilo 1, Labo, Camarines Norte
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-22-0014169

₱42,786,246.00 · FY2022

Released to Camarines Norte DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱11,582,097.10

Progress

Reported complete (DPWH)

Start Date

June 9, 2022

Target End

October 10, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.