1,766 DPWH public works projects are recorded in Camarines Norte (Region V), with start dates from 2016 to 2025. Recorded contract values total about ₱31,408,043,830.50. 1,591 are recorded at 100% progress and 276 are flood control works. Figures are as recorded by DPWH; they are not findings.
Largest recorded projects
- Construction of Flood Mitigation Structure Along Calagdo River, Barangay Tuaca, Basud Camarines Norte₱154,399,262.80
- Construction of Flood Mitigation Structure Along Minasag River, Barangay San Lorenzo and Barangay Rizal, Santa Elena, Camarines Norte₱154,399,195.20
- Construction of Flood Control Structure Along Labo River (Downstream), Barangay Matanlang, Labo, Camarines Norte (Package Iv), Brgy. Matanlang, Labo, Camarines Norte₱144,749,981.54
- Construction of Flood Control, Barangay Mabilo I - Mabilo Ii, Labo, Camarines Norte (Package 3), Brgy. Mabilo I - Mabilo Ii, Labo, Camarines Norte₱144,749,937.46
- Construction of Flood Control Structure Along Labo River (Downstream), Barangay Matanlang, Labo, Camarines Norte (Package Ii), Brgy. Matanlang, Labo, Camarines Norte₱144,749,864.05
- Construction of Flood Control Structure Along Labo River (Downstream), Barangay Matanlang, Labo, Camarines Norte (Package Iii), Brgy. Matanlang, Labo, Camarines Norte₱144,749,835.75
- Construction of Flood Control Structure Along Busigon River at Matanlang-Mabilo Ii, Labo, Camarines Norte (Phase 5), Brgy. Matanlang, Labo, Camarines Norte₱144,749,743.10
- Construction of Flood Control Structure Along Busigon River at Matanlang-Mabilo Ii, Labo, Camarines Norte (Phase 6), Brgy. Matanlang, Labo, Camarines Norte₱144,749,646.56
- Construction of Flood Control Structure Along Matogdon River, Barangay Lugui, Labo, Camarines Norte (Package Ii), Brgy. Lugui, Labo, Camarines Norte₱144,749,351.14
- Construction of Flood Control Structure Along Matogdon River, Barangay Lugui, Labo, Camarines Norte (Package I), Brgy. Lugui, Labo, Camarines Norte₱144,738,963.38
- Construction of Flood Control Structure at Barangay Anahaw - Barangay Malasugui, Labo, Camarines Norte (Busigon River)₱144,030,966.10
- Construction of Road at Barangay Tigbinan, Labo, Camarines Norte₱140,414,319.79
- Construction of Flood Control Structure Along Busigon River, Phase I, Barangay Tigbinan, Labo, Camarines Norte₱140,411,770.70
- Construction of Flood Mitigation Structure (Phase Iii), Barangay Lugui, Labo, Camarines Norte₱140,408,978.86
- Construction of Road at Barangay Mabilo 1, Labo, Camarines Norte₱140,407,284.29
- Construction of Flood Control at Brgy. Mabilo I - Mabilo Ii (Labo River) Labo, Camarines Norte (Package 4), Brgy. Mabilo I - Brgy. Mabilo Ii, Labo, Camarines Norte₱140,405,944.53
- Construction of Flood Control Structure Along Busigon River, Phase Iii, Barangay Guisican, Labo, Camarines Norte₱140,396,927.85
- Construction of Flood Control Structure Along Busigon River, Phase Ii, Barangay Guisican, Labo, Camarines Norte₱140,395,214.89
- Construction of Flood Control Structure Along Matogdon River, Phase Ii, Barangay Anahaw, Barangay Bautista and Barangay Mabilo Ii, Labo, Camarines Norte₱140,395,076.05
- Construction of Flood Control Structure, Barangay Cabusay, Labo Camarines Norte₱140,388,718.33
- Construction of Flood Control at Brgy. Mabilo I - Mabilo Ii (Labo River) Labo, Camarines Norte (Package 5), Brgy. Mabilo I, Labo, Camarines Norte₱140,387,056.13
- Construction of Flood Control Structure Along Busigon River, Phase I, Barangay Guisican, Labo, Camarines Norte₱140,382,652.84
- Construction of Flood Control Structure Along Matogdon River, Phase I, Barangay Anahaw, Barangay Bautista and Barangay Mabilo Ii, Labo, Camarines Norte, Brgy Anahaw - Bautista, Labo, Camarines Norte₱140,361,266.28
- Construction of Water Supply System, Sta. Elena, Camarines Norte₱138,550,860.40
- Construction/Improvement of Labo River Flood Mitigation Structure, Brgy. Bakiad, Labo, Camarines Norte₱133,128,606.10