Flood Control and Drainage25FC0026

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BUSIGON RIVER, PHASE I, BARANGAY GUISICAN, LABO, CAMARINES NORTE

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BUSIGON RIVER, PHASE I, BARANGAY GUISICAN, LABO, CAMARINES NORTE is a DPWH-tracked public work in Camarines Norte DEO, Region V. Reported contract value: ₱140,382,652.84. Status: Past target date (DPWH On-Going). Contractor on record: WAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS. Figures trace to dpwh.

Camarines Norte DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control / Mitigation at Brgy. Tigbinan, Labo, Camarines Norte (Phase 5)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Camarines Norte DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱140,382,652.84

Progress

Past target date (DPWH On-Going)

Start Date

April 3, 2025

Target End

January 20, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.