CONSTRUCTION OF CONCRETE SLOPE PROTECTION STRUCTURE ALONG GABOR RIVER, PHASE 2, SAN FELIPE, ZAMBALES
CONSTRUCTION OF CONCRETE SLOPE PROTECTION STRUCTURE ALONG GABOR RIVER, PHASE 2, SAN FELIPE, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱47,588,896.17. Status: Past target date (DPWH On-Going). Contractor on record: PASCAL CONST. Figures trace to dpwh.
Satellite images processing — before/after tiles will appear here after the next batch run.
Total Contract Cost