Flood Control and Drainage19BE0051

CONSTRUCTION OF RIVER FLOOD CONTROL, CAGAYAN RIVER BRGY. PARAGU, TUMAUINI, ISABELA

CONSTRUCTION OF RIVER FLOOD CONTROL, CAGAYAN RIVER BRGY. PARAGU, TUMAUINI, ISABELA is a DPWH-tracked public work in Isabela 1st DEO, Region II. Reported contract value: ₱18,618,088.93. Status: Reported complete (DPWH). Contractor on record: EGB CONST CORP FORMERLY: EGB CONST. Figures trace to dpwh.

Isabela 1st DEO, Region II
Region: Region II

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    SARO SARO-BMB-A-19-0010322 · · release to the district office, not itemized per project

    Possible match · score 0.65

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 19BE0051 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-02-22 → 2025-05-20

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Isabela

Based on the coordinates published with the DPWH record and NOAH file Isabela.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF RIVER  FLOOD CONTROL, CAGAYAN RIVER BRGY. PARAGU, TUMAUINI, ISABELA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-19-0010322

₱-12,066,096.00 · FY2019

Released to Abra District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

646 projects · ₱29.0B total · 49 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGE - MINANGA BR. (B01129LZ) ALONG MAHARLIKA HIGHWAY

Region II, Region II

2025₱241.2M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - DAANG MAHARLIKA (LZ) - K0399 + 008 - K0400 + 009, K0405 + 885 - K0406 + 340, K0439 + 000 - K0439 + 557, K0444 + 230 - K0447+ 200, K0447 + 7

Region II, Region II

2024₱213.3M
Past target date (DPWH On-Going)

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) COASTAL ROADS/CAUSEWAY FOR ENVIRONMENTAL PROTECTION/CONSERVATION- CONSTRUCTION OF MANSALAY COASTAL ROAD, DEL MUNDO SECTION, MANSALAY, ORIENTAL MINDORO

Region IV-B, Region IV-B

2023₱212.3M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- SECONDARY ROADS- MINDORO WEST COASTAL ROAD, K0417+000 - K0445+498 (INTERMITTENT SECTIONS), ABRA DE ILOG, OCC. MINDORO

Region IV-B, Region IV-B

2025₱202.1M
Past target date (DPWH On-Going)
No sat.

CSSP-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION (COMPLETION) OF TUROD-BANQUERO BRIDGE, REINA MERCEDES, ISABELA

Isabela 3rd DEO, Region II

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-SIPAG-INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS)-CONSTRUCTION OF DIVERSION/BY-PASS ROAD OF CORY AQUINO BOUL

Region V, Region V

2025₱192.0M
Past target date (DPWH On-Going)
View all 646 projects →

4. Implementation

Contract Amount

₱18,618,088.93

Progress

Reported complete (DPWH)

Start Date

May 29, 2019

Target End

December 10, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.