Buildings and Facilities19EF0119

CONSTRUCTION OF MULTI-PURPOSE BUILDING PURING, BATARAZA, PALAWAN

CONSTRUCTION OF MULTI-PURPOSE BUILDING PURING, BATARAZA, PALAWAN is a DPWH-tracked public work in Palawan 2nd DEO, Region IV-B. Reported contract value: ₱990,072.94. Status: Reported complete (DPWH). Contractor on record: MAINTIN CONST. Figures trace to dpwh.

Palawan 2nd DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-19-0005439

₱11,776,013.00 · FY2019

Released to Regional Office - V (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

65 projects · ₱272.7M total · 0 flags

4. Implementation

Contract Amount

₱990,072.94

Progress

Reported complete (DPWH)

Start Date

September 16, 2019

Target End

January 13, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.