Rehabilitation / Major Repair of Flood Control Structure23DC0043

Rehabilitation of Slope Protection along Cabaong Br. (B04540LZ) - along Santo Tomas, Batangas

Rehabilitation of Slope Protection along Cabaong Br. (B04540LZ) - along Santo Tomas, Batangas is a DPWH-tracked public work in CITY OF SANTO TOMAS (BATANGAS), BATANGAS, Region IV-A. Reported contract value: ₱29,398,381.60. Status: Reported complete (DPWH). Contractor on record: VAN MAKJAY CONST. Figures trace to sumbong.

CITY OF SANTO TOMAS (BATANGAS), BATANGAS, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Slope Protection with Flood Mitigation Structure along Pinagtung-Ulan Bridge, San Jose, Batangas
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-23-0027183

₱1,300,000.00 · FY2023

Released to Central Luzon State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

30 projects · ₱312.2M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS, PALICO - BALAYAN - BATANGAS RD

Batangas 3rd DEO, Region IV-A

2024₱68.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING - SECONDARY ROADS, PALICO-BALAYAN-BATANGAS RD

Batangas 3rd DEO, Region IV-A

2025₱38.2M
Past target date (DPWH On-Going)
No sat.

Construction of Slope Protection, Brgy. Poblacion, San Nicolas, Batangas

SAN NICOLAS (BATANGAS), BATANGAS, Region IV-A

2023₱29.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM -TRIP), TAAL LAKE CIRCUMFERENTIAL ROAD (AGONCILLO SECTION), AGONCILLO, BATANGAS

Batangas 3rd DEO, Region IV-A

2025₱16.7M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ELEMENTARY AND SECONDARY CLASSROOMS (BATCH 1) UNDER THE DEPED'S CY 2023 BASIC EDUCATION FACILITIES FUND, CONSTRUCTION OF 2STYCL, CORAL NA MUNTI NATIONAL HIGH SCHOOL, AGONCILLO, BATANGAS

Batangas 3rd DEO, Region IV-A

2023₱15.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP), BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, SAN NICOLAS, BATANGAS

Batangas 3rd DEO, Region IV-A

2024₱14.8M
Reported complete (DPWH)
View all 30 projects →

4. Implementation

Contract Amount

₱29,398,381.60

Progress

Reported complete (DPWH)

Start Date

March 10, 2023

Target End

December 4, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.