Bridges16A00128

RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES ALAMBIQUE BRIDGE (B00619LZ) ALONG MNR, CANDON, ILOCOS SUR

RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES ALAMBIQUE BRIDGE (B00619LZ) ALONG MNR, CANDON, ILOCOS SUR is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱3,023,622.11. Status: Reported complete (DPWH). Contractor on record: SYNDTITE CONST CORP FORMERLY: R C TAGALA CONST. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

466 projects · ₱13.0B total · 1 flags

Other projects by this contractor

View all 466 projects →

4. Implementation

Contract Amount

₱3,023,622.11

Progress

Reported complete (DPWH)

Start Date

November 2, 2016

Target End

March 16, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.