Construction of Flood Mitigation Structure24K00194

Construction of Flood Control Structure along Puerto Creek, Package 1, Cagayan de Oro City

Construction of Flood Control Structure along Puerto Creek, Package 1, Cagayan de Oro City is a DPWH-tracked public work in CAGAYAN DE ORO CITY (CAPITAL) (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X. Reported contract value: ₱110,634,633.40. Status: Reported complete (DPWH). Contractor on record: OLISON CORP / MAMSAR CONST AND INDUSTRIAL CORP. Figures trace to sumbong.

CAGAYAN DE ORO CITY (CAPITAL) (MISAMIS ORIENTAL), MISAMIS ORIENTAL, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure Arroyo Creek, barangay 1, Cagayan de Oro
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-24-0002227

₱17,744,000.00 · FY2024

Released to Division of Tarlac (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-24-0007532

₱1,152,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-24-0017295

₱458,450.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROX-24-0007533

₱106,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱110.6M total · 0 flags

4. Implementation

Contract Amount

₱110,634,633.40

Progress

Reported complete (DPWH)

Start Date

May 3, 2024

Target End

April 12, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.