CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITH PUMPING STATION AND FLOOD GATE AT MAMBOG CREEK, MALOLOS CITY, BULACAN (PHASE III)
CONSTRUCTION OF FLOOD MITIGATION STRUCTURE WITH PUMPING STATION AND FLOOD GATE AT MAMBOG CREEK, MALOLOS CITY, BULACAN (PHASE III) is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱42,697,065.92. Status: Ongoing (DPWH-reported) (Not Yet Started (DPWH-reported)). Contractor on record: FERDSTAR BUILDERS INC. Figures trace to dpwh.
Satellite images processing — before/after tiles will appear here after the next batch run.
Total Contract Cost